GDOT to Close Southbound GA 400 Lanes Next Week

Lane closures are needed overnight during construction on the Ga. 400 Buckhead pedestrian bridge.

By Bob Pepalis 

If you plan to drive on Ga. 400 next week between 8 p.m. and 5 a.m., be prepared to slow down for lane closures underneath the MARTA Buckhead pedestrian bridge that's under construction.

The lane closures are needed to accommodate bridge deck patching and sign installation.

The southbound lanes will be closed from Monday, Jan. 27-Saturday, Feb. 1 by the Ga. Department of Transportation between mile markers 2 and 3.

Find out what's happening in Roswellwith free, real-time updates from Patch.

Southbound Lane Closures

(To remove overhand decking and patch bridge deck.)

Find out what's happening in Roswellwith free, real-time updates from Patch.

8 p.m.-5 a.m.

Monday, Jan. 27: Right lane of Ga. 400

Tuesday, Jan. 28: Right lane of Ga. 400

Wednesday, Jan. 29: Right lane of Ga. 400

Thursday, Jan. 30: Two left lanes of Ga. 400 to remove overhand decking, patch bridge deck  and set "MARTA" sign

Friday, Jan. 31: Two left lanes of Ga 400

Saturday, Feb. 1: Two left lanes of Ga 400

The Ga. 400 pedestrian bridge project includes:

  • A new entrance on the north end of the existing Buckhead Station
  • Pedestrian bridge over north and southbound lanes of GA 400
  • An elevator/stair tower, sidewalk, and bridge connection on the east side of GA 400
  • Sidewalk access to elevated walkway from Tower Place to connect to the bridge on the west side of GA 400

Learn more online about other GA 400 Improvement Projects.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here